Case study 06 / Industrial
Mechanical plant and workspace upgrade for Edwards Vacuum.
£1.6m upgrade in Burgess Hill: a new mezzanine floor, offices, and mechanical and electrical services.
The brief
Edwards Vacuum needed its Burgess Hill facility upgraded, combining new workspace with a major mechanical plant upgrade.
Project management
Reeves Projects provided the project management. The work added a mezzanine floor and new offices, and upgraded the lighting, power and mechanical services, including air conditioning, plumbing, heating and drainage.
Scope of works
- Mezzanine floor
- New offices
- Lighting and power
- Air conditioning
- Plumbing and heating
- Drainage
The outcome
Structural, fit out and building services work had to be sequenced so each trade could finish in the right order. The project was completed on time and within budget.